Timing verification (maximum or average restraint) – Basler Electric BE1-11t User Manual

Page 421

background image

9424200995 Rev H

409

Step 5: Slowly increase the A-phase current in CT circuit 1 or 2 until OUT2 closes and record the

pickup. This should occur at 0.70 A

±0.05 A. Verify that there is an 87A target on the front-panel

display.

Step 6: Slowly decrease the A-phase current in CT circuit 1 or 2 until OUT2 reopens and record the

dropout. See the functional test report for acceptable ranges.

Step 7: Reset to the current levels in step 5 and reset all targets.

Step 8: Slowly decrease the A-phase current in CT circuit 1 or 2 until OUT2 closes and record the

pickup. This should occur at 0.30 A

±0.05 A. Verify that there is an 87A target on the front-panel

display.

Step 9: Slowly increase the A-phase current in CT circuit 1 or 2 until OUT2 reopens and record the

dropout. See the functional test report for acceptable ranges.

Step 10: To test the Restraint Slope 1 setting, connect two balanced three-phase current sources to the

BE1-11t in ABC rotation: 3.0

∠0°, 3.0∠–120°, 3.0∠120° amps to terminals D1 through D6 and

3.0

∠180°, 3.0∠60°, 3.0∠–60° amps to terminals F1 through F6 (1.5x tap).

Step 11: Slowly increase the A-phase current in CT circuit 1 or 2 until OUT2 closes and record the

pickup. This should occur at 3.67 A

±0.07 A. Verify that there is an 87A target on the front-panel

display.

Step 12: Reset to the current levels in step 9 and reset all targets.

Step 13: Slowly decrease the A-phase current in CT circuit 1 or 2 until OUT2 closes and record the

pickup. This should occur at 2.46 A

±0.05 A. Verify that there is an 87A target on the front-panel

display.

Step 14: To test the Restraint Slope 2 setting, connect two balanced three-phase current sources to the

BE1-11t in ABC rotation:6.5

∠0°, 6.5∠–120°, 6.5∠120° amps to terminals D1 through D6 and

6.5

∠180°, 6.5∠60°, 6.5∠–60° amps to terminals F1 through F6 (3.25x tap).

Step 15: Slowly increase the A-phase current in CT circuit 1 or 2 until OUT2 closes and record the

pickup. This should occur at 8.25 A

±0.17 A. Verify that there is an 87A target on the front-panel

display.

Step 16: Reset to the current levels in step 12 and reset all targets.

Step 17: Slowly decrease the A-phase current in CT circuit 1 or 2 until OUT2 closes and record the

pickup. This should occur at 5.32 A

±0.11 A. Verify that there is an 87A target on the front-panel

display.

Step 18: (Optional.) Repeat steps 1 through 17 for the B-phase and C-phase current inputs.

Step 19: (Optional.) Repeat steps 1 through 18 for settings group 1, 2, and 3.

Timing Verification (Maximum or Average Restraint)

Step 1: Use BESTCOMSPlus to verify the operational settings in Table 193 (Maximum) or 2 (Average)

and logic in Figure 265. Reset all targets.

Step 2: Prepare to monitor the 87 timings. Timing accuracy is verified by measuring the elapsed time

between OUT2 (pickup) and OUT1 (trip) closing.

Step 3: Connect two balanced three-phase current sources to the BE1-11t in ABC rotation: 3.0

∠0°,

3.0

∠–120°, 3.0∠120° amps to terminals D1 through D6 and 3.0∠180°, 3.0∠60°, 3.0∠–60° amps

to terminals F1 through F6.

Step 4: Slowly increase the A-phase current in CT circuit 1 or 2 until OUT2 closes. Record the time

between OUT2 and OUT1 closing. This should be 100 ms

± (50 ms + 2 cycles).

Step 5: (Optional) Repeat steps 1 through4 for settings group 1, 2, and 3.

BE1-11t

Phase Current Differential (87) Test