PROFIBUS−DP
Before switching on
Commissioning
11.2
11.2.1
L
11.2−1
EDSPM−TXXX−9.0−11/2009
11.2
PROFIBUS−DP
11.2.1
Before switching on
Prior to supply voltage connection, check
l
the wiring for completeness, short circuits and earth faults
l
the wiring of the fieldbus
– A bus terminating resistor has to be connected to the first and the last
node.
l
spatial cable separation from signalling and mains cables.
)
Note!
After connecting the supply voltage, the modules of the I/O
system IP20 are initialised. During the initialisation, the modules
cannot be parameterised.
l
Initialisation time: approx. 10 s