12 - pump/dispenser automatic test, Icr - pump activation test (optional), 12 – pump/dispenser automatic test – Gasboy CFN Series Site Controller III Start-up User Manual
Page 79: Important information

MDE-4793A CFN Series Site Controller III Start-up Manual for CFN III Versions 3.5 and above · November 2008
Page 73
ICR - Pump Activation Test (Optional)
Pump/Dispenser Automatic Test
12 – Pump/Dispenser Automatic Test
The automatic test verifies pump operation and ensures that transactions are accurately
recorded and that quantities and prices agree with those displayed on the pumps. As each
transaction is completed, it should print on the data terminal attached to the logger port. For
remote sites not using the monitor mode, either a data terminal can be temporarily connected
to the logger port or the information will have to be manually polled. The steps outlined in this
section indicate the proper procedure for testing and the expected results.
Before the pumps can be properly tested in automatic using the ICR and/or console,
the CFN system must be configured for the pulser type on each pump (for example,
gallon wheel, money wheel, electronic register) and the pulser rate (for example, 1:1,
10:1, 100:1, 500:1). To verify this, perform the print pump command, P PU, and verify
the rate column on the printout with the physical pumps at the site.
Note: The system counts edges, not pulses. For example: 10:1 on gallons = 20 edges
per gallon, 100:1 on gallons = 200 edges per gallon. If you have a penny pulsing
pump (for example, one pulse per penny), a 10:1 pulse ratio would yield 200
edges per dollar. When you do a P PU command, the edges figure is shown in
the RATE column.
When using pumps and/or dispensers at retail sites, the proper price must be set on
the pump and loaded in the system to verify proper registration. The fallback price
(Level 0) should be the same as the posted prices; if using dollar pulsers it must be the
same.
If you are using the SC III interfaces to electronic pumps, pulse rates are not important.
On Gilbarco pumps/dispensers, pulse units must be $ (dollar).
If pulse rates need to be changed, open switch SW4 on the back of the CFN III. Once
the necessary changes are made, ensure that you return the switch to its original
position.
IMPORTANT INFORMATION
ICR - Pump Activation Test (Optional)
To perform the ICR - Pump Activation Test, proceed as follows:
1
Place all the override switches, located in the PCU(s) (refer to
on
ON position.
2
Using the test cards (provided with each system), select Hose 1.
3
Turn on Hose 1 using the pump handle.
Hose 1 should reset and be able to dispense product.
4
Dispense some product with Hose 1.