Dc power, System approvals, Customer knowledge – Gasboy CFN Series Site Controller III Start-up User Manual
Page 122: Attach printouts, Parts used

Gasboy Motor Fuel Management System
Page 116
MDE-4793A CFN Series Site Controller III Start-up Manual for CFN III Versions 3.5 and above · November 2008
9. DC POWER
Site Controller/Islander: +5 VDC +12 VDC -12 VDC
PCU(s): +5 VDC +12 VDC
ICR(s): +5 VDC +12 VDC
Current Loop Interface: +5 VDC +12 VDC -12 VDC
Consoles: +5 VDC +12 VDC -12 VDC +9 VDC
FPR(s): +5 VDC
10. SYSTEM APPROVALS
Customer Comments:
I am satisfied with the installation of the Gasboy Site Manager: Date:
CFN System and have been trained in its use and Start-up Tech: Date:
operation.
11. CUSTOMER KNOWLEDGE
Time Spent on Training: Names of People Trained:
Were test cards locked out? Y/N Who were test cards left with?
Was backup copy made of system and any configuration changes? Y/N
Remarks:
(Use additional sheets if necessary)
12. ATTACH PRINTOUTS
Generate and attach printout showing a few transactions with quantity, pump fuel assignments,
limitation codes, authorization codes, and pulse rates. Use the commands PR DA, PR TR, PR PU, PR
AU, PR LIM, PR DI, PR PRI, PR PRO, and STATUS.
13. PARTS USED
Return defective parts with completed Gasboy Service Report. Please return white, yellow, and
pink copies of report in box with parts