Synchronizing erdb on redundant servers, Synchronizing erdb on redundant servers -63 – Rockwell Automation 1757-SWKIT3200 ProcessLogix R320.0 Installation and Upgrade Guide User Manual
Page 83

Publication 1757-IN032B-EN-P - April 2001
System Software Upgrade Procedures 1-63
5. When the replica creation has completed, click Yes to start the ER
Replicator service.
6. Close DbAdmin.
Synchronizing ERDB on Redundant Servers
Use the following procedure to synchronize the ERDB after the
redundant Servers are restarted as noted in the previous section.
1. On the SERVERB node, click Start
⇒
Programs
⇒
ProcessLogix
Engineering Tools
⇒
Control Builder.
2. In the Login dialog box, make these entries:
a. Key in >mngr< as the default User Name.
b. Key in >mngr1< as the default Password.
c. Key in the name of the SERVERB node in the Server Name
field.
3. Click OK.
4. Does the synchronization status field on the right side of the status
bar at the bottom of the display read “SYNC”.
•
If answer is Yes, go to Step 9.
•
If answer is No, go to Step 5.
5. Click Tools to open the pulldown menu.
•
Confirm that a checkmark appears before Enable Engineering
Database Synchronization selection.
•
If a checkmark does not appear, click Enable Engineering
Database Synchronization to enable it and display the
checkmark.
6. Click OK to acknowledge the warning prompt.
7. Verify that the synchronization status field on the right side of the
status bar at the bottom of the display now reads “SYNC”.
8. Click Tools and confirm that a checkmark appears by the Enable
Engineering Database Synchronization selection.
9. Click Tools
⇒
Synchronize Engineering Database Now.
10. Read the warning prompt message and click OK to start ERDB
synchronization.