Initiating redundant controller switchover, Initiating redundant controller switchover -41 – Rockwell Automation 1757-SWKIT3200 ProcessLogix R320.0 Installation and Upgrade Guide User Manual
Page 61

Publication 1757-IN032B-EN-P - April 2001
System Software Upgrade Procedures 1-41
5. Download each CPM and SRM to its given Controller.
6. Download the database (contents of each CPM’s CEE) to the
Controller.
7. In the Monitoring tab, activate the CEE and all of its components
in a given Controller.
Initiating Redundant Controller Switchover
For ProcessLogix system with redundant Controllers, use the following
procedure to initiate a Backup (Secondary) Controller switchover to
Primary Controller in a Redundant Chassis Pair (RCP).
1. Click Start
⇒
Programs
⇒
ProcessLogix Engineering
Tools
⇒
Control Builder.
2. In the Login dialog box, make these entries:
a. Key in >mngr< as the default User Name.
b. Key in >mngr1< as the default Password.
c. Key in >localhost< in the Server Name field.
3. Click OK.
4. Click the Monitoring tab. Click the Root directory to open it.
5. Double-click the Primary SRM icon
to call up the SRM block
form.
6. Click the Summary tab, if it is not already on display.
7. Confirm that the displayed Secondary Readiness status is
SYNCHRONIZED.
•
If the status is Synchronized, go to Step 8.
•
If the status is something other than Synchronized, contact
Rockwell Automation Technical Support for help in
determining why the status is not Synchronized.
ATTENTION
!
This procedure assumes that you have at least loaded
the CPM/CEE and SRM Control Builder
configurations to the 1757-PLX52s and 1757-SRMs in
the RCP and that the RCP is powered.