Operator’s manual – Great Plains DICKEY-john IntelliAg Planter-Drill Control L3 User Manual
Page 125
OPERATOR’S MANUAL
IntelliAg PDC User 2 & 3
11001-1501-200811
SYSTEM CONFIGURATION / 117
Figure 73
Minimum Override
MASTER SW TIMEOUT
Master Switch Timeout determines the length of time before the system
disables the operate function after ground speed is 0 (zero) if the master
switch remains in the ON position. After the delay time elapses, an alarm is
issued stating that the master switch must be toggled OFF/ON before the
system will restart.
GROUND FAIL ALARM DELAY
Alarm Delay determines the length of time after the ground speed goes to
zero and seed flow continues before the alarm sounds. This alarm only
applies when all control channels are disabled and the system is running in
a Planter Monitor Only mode.
PRECHARGE GROUND SPEED
Precharge Ground Speed is the speed the system will use when Precharge
has been enabled for a control channel and Precharge Ground Speed
greater than 0 must be entered to operate.
FLUSH ENABLE SPEED
Flush Enable Speed is the speed the system will use when Flush Enable is
pressed to open the valve and dispense material. The Flush Enable feature
can only be activated when the implement is stopped.
IMPLEMENT LIFT
If an implement lift switch is used, the implement lift status must be enabled.
While operating, an alarm condition will occur if the Master Switch is off for
more than 5 to 10 seconds, the implement is down, and ground speed is
greater than zero. An Alarm Cancel button allows the alarm to be
deactivated during the current power cycle. If an implement lift switch is not
required, this function should be disabled.
300
MIN
8.0
Minimum
Override
set at 8 mph