3.6.7.2. Mounting of detector (SX3-D0)
Mount the detector using the following procedure:
(1) Provide wire rope for the upstream and the
downstream detectors. Make sure that the length of
the wire rope is longer than the circumference of the
pipe.
Fig. 3-32
(2) Lay the wire rope around the pipe at the position of
the upstream detector. Then hook the mounting
spring onto the wire rope ends.
Fig. 3-33
(3) Spread silicone filler over the whole transmitting side
of the detector smoothly without bubbles. Ensure
there are no air gaps or bubbles.
Fig. 3-34
(4) Clean the surface of the pipe, then mount the detector.
Fig. 3-35
(5) Press the detector against the pipe. Align the center of
the detector using the intersection of the marking
line and the mounting dimension as a guide.
Fig. 3-36
(6) Make sure that the center mark on the detector is
aligned with the marking line. Then, connect the
coaxial cable to the transmitter.
Note) Do not pull the coaxial cable. If it is pulled,
the detector is shifted which results in
incorrect measurements due to poor contact.
Fig. 3-37