AGS Voltage Start

There are three voltage start set points in AGS mode that the user can select.

24 Hour Start

2 Hour Start

2 Minute Start

If the voltage drops below the voltage setting in these three menu items, a timer starts counting down.
When the timer reaches zero (0), a start command is sent to the generator. The

Quiet Time

settings

overrides the starting set points, preventing the generator from starting automatically. The exception is

2 Minute Start

, which is considered an emergency start set point and which will start the generator

regardless of

Quiet Time

settings.

After a generator is started due to a

Voltage Start

setting, it will be stopped when the inverter completes

the battery charging cycle.

IMPORTANT:

If the

DC Generator

is set to

Y

, the generator will only stop after reaching the DC

generator parameters shown in Figure 143 on page 116.

Figure 145 MATE3/AGS/Voltage Start Screen

AGS Load Start

Load Start

will start a generator whenever the total system AC load wattage exceeds the

Start

set point

for the programmed amount of time (

Delay

). The generator will then be stopped when the AC load has

dropped below a

Stop

set point for a programmed amount of time (

Delay

).

When the generator is running because of

Load Start

, the inverter system will charge the batteries.

However, it is not programmed to perform a complete charge cycle. If the generator stops upon reaching
its

Stop

criteria/set point, the charge might not be completed.

Figure 146 MATE3/AGS/Load Start Screen

IMPORTANT:

Large, instantaneous loads can still overload the inverter prior to the generator
starting and getting synchronized with the inverter.
See the inverter Operator’s Manual for instructions on resetting the inverter following
an overload.

Set Points:

EnabledN=No, Y=Yes
Start0 to 50 kW Delay 1 to 240 minutes
Stop0 to 49 kW Delay 1 to 240 minutes

Set Points:

24 Hour Start EnableN=No, Y=Yes Voltage xx.x

(inverter-dependent)

2 Hour Start EnableN=No, Y=Yes Voltage xx.x

(inverter-dependent)

2 Minute Start EnableN=No, Y=Yes Voltage xx.x

(inverter-dependent)