245

4.7

I/O Signal Timings

When any of the control signal is turned ON to perform the operation of the actuator using the PLC's

sequence program, the response (status) is returned to the PLC. The maximum response time is expressed

using the following formula.

Maximum response time (msec)䋽Yt+Xt+3+ command processing time (operation time, etc.)

Yt: Master Stationĺslave transmission delay time

Xt: SlaveĺMaster Station Transmission Delay Time

Master Stationĺ For the master station o slave transmission delay (Yt) and slave o master station

transmission delay (Xt), refer to the Operation Manuals for the EtherNet/IP master unit and PLC installed in

the master unit.

Filed Network Transmission

Delay Time

Command

processing time

PLC sequence program

Control signal

Status signal

SCON

Control signal

Status signal

Master station o slave

station transmission

delay time (Yt)

Slave station o master

station delay time (Xt)