beautypg.com

2 mounting – Comtech EF Data CDM-710G User Manual

Page 50

background image

CDM-710G High-Speed Satellite Modem

Revision 1

Installation

MN-CDM710G

2–2

2.2

Mounting

If the modulator is to be mounted in a rack, ensure that there is adequate clearance for ventilation,
particularly at the sides. In rack system where there is high heat dissipation, forced air-cooling
must be provided by top or bottom mounted fans or blowers. Under no circumstance should the
highest internal rack temperature be allowed to exceed 50

°C (122°F).

2.2.1

Method A: Optional Rear-Mounting Support Brackets

Install optional rear-mounting support brackets using mounting kit KT/6228-2:

Optional Rear-Mounting Support Brackets Kit KT/6228-2

Quantity

CEFD Part Number

Description

2

HW/10-32SHLDR

Screw, #10 Shoulder

4

HW/10-32FLT

Washer, #10 Flat

2

HW/10-32SPLIT

Washer, #10 Split

2

HW/10-32HEXNUT

Nut, #10 Hex

2

FP/6138-1

Bracket, Rear Support

4

HW/10-32x1/2RK

Bolt, #10 Rack Bracket

The tools required for this installation are a medium Phillips

screwdriver and a 5/32-inch

SAE Allen

Wrench. The kit is installed as illustrated in Figure 2-1 and per the following

procedure:

Step

Description

1

Secure the #10 shoulder screws to the unit chassis through the rear right and left
side mounting slots, using the #10 flat washers, #10 split washers, and #10 hex
nuts as shown.

2

Install the rear support brackets onto the equipment rack threaded rear mounting
rails, using the #10 rack bracket bolts.

3

Mount the unit into the equipment rack, ensuring that the shoulders of the #10
shoulder screws properly engage into the rear support bracket slots.


This manual is related to the following products: