Complete the CP PM installation

Testing the CP PM Call Servers

Procedure 24
Testing CP PM Call Server 0

At this point in the installation, CP PM Call Server 0 is tested from active CP
PM Call Server 1. Upon successful completion of these tests, call processing
is switched and the same tests are performed on CP PM Call Server 1 from
active CP PM Call Server 0. As a final step, call processing is then switched
again to CP PM Call Server 1.

From active CP PM Call Server 1, perform the following tests on CP PM
Call Server 0
:

1

Perform a redundancy sanity test:

2

Check the LCD states

a.

Perform a visual check of the LCDs.

b.

Test and LCDs:

c.

Check that the LCD display matches the software check.

3

Test the System Utility card

LD 135

STAT CPU

Get status of CPU and memory

TEST CPU

Test the CPU

LD 135

TEST LEDs

Test LEDs

DSPL ALL

LD 135

Load program

STAT SUTL

Get the status of the System Utility card

TEST SUTL

Test the System Utility card