Test the cp pm call server, Procedure 21 testing the cp pm call server – Nortel Networks 1000E User Manual

Page 133

background image

Installing software on the CS 1000E

Page 133 of 466

Communication Server 1000E

Installation and Commissioning

Test the CP PM Call Server

Procedure 21
Testing the CP PM Call Server

1

Verify that the CP PM Call Server is active.

2

Check dial-tone.

3

Verify that the CP PM Call Server is active, redundant, and single.

4

Make internal, external, and network calls.

5

Check attendant console activity.

6

Check IP Peer networking for incoming and outgoing calls.

7

Check applications (CallPilot, Symposium, and so on).

End of Procedure

Install the software on the second CP PM Call Server

Procedure 22
Installing the software on the second CP PM Call Server

1

Attach the ELAN and TLAN cables to the CP PM faceplate connectors
between the CP PM Call Servers.

2

Complete procedures 22 through 27 for the second CP PM Call Server.

3

Each CP PM Call Server can be named: CP PM Call Server 1 and CP PM
Call Server 0.

Note: Do not install ELAN and TLAN cables at this time.

End of Procedure

LD 135

Load program

STAT CPU

Get the status of the CPUs