Test the cp pm call server, Procedure 21 testing the cp pm call server – Nortel Networks 1000E User Manual
Page 133
Installing software on the CS 1000E
Page 133 of 466
Communication Server 1000E
Installation and Commissioning
Test the CP PM Call Server
Procedure 21
Testing the CP PM Call Server
1
Verify that the CP PM Call Server is active.
2
Check dial-tone.
3
Verify that the CP PM Call Server is active, redundant, and single.
4
Make internal, external, and network calls.
5
Check attendant console activity.
6
Check IP Peer networking for incoming and outgoing calls.
7
Check applications (CallPilot, Symposium, and so on).
End of Procedure
Install the software on the second CP PM Call Server
Procedure 22
Installing the software on the second CP PM Call Server
1
Attach the ELAN and TLAN cables to the CP PM faceplate connectors
between the CP PM Call Servers.
2
Complete procedures 22 through 27 for the second CP PM Call Server.
3
Each CP PM Call Server can be named: CP PM Call Server 1 and CP PM
Call Server 0.
Note: Do not install ELAN and TLAN cables at this time.
End of Procedure
LD 135
Load program
STAT CPU
Get the status of the CPUs