beautypg.com

Testing the dut – EXFO IQS-12004B DWDM Passive Component Test System for IQS-500 User Manual

Page 187

background image

Automating or Remotely Controlling the System

DWDM Passive Component Test System

175

Testing the DUT

Testing the DUT

Once the previous steps have been successfully completed and the
device(s) under test—DUT(s)—have been properly connected, the system
is ready to perform IL, PDL, and ORL measurements of the DUT(s).

Note: Only the MultiPath Testing option allows you to test more than a device at a

time and devices having a variable number of In ports and Out ports.

For more information, see Connecting DUT and Modules on page 67 and
Starting the ORL Measurement Scan on page 69.

With the MultiPath Testing Option, the DUT(s) have to be connected
between the power meter and the switch.

The COM properties and methods associated with this step are Position
(see page 341), AcqIlDut (see page 274), AcqIlPdlDut (see page 275),
AcqOrlMandrelDut (see page 275).

The SCPI commands associated with this step are ACQuisition:IL (see page
253), ACQuisition:ILPDl (see page 253), ACQuisition:ORL (see page 254).