Nulling Electrical Offsets

This feature allows you to perform an electrical offset nulling of the power
meters. For more information, see Nulling Electrical Offsets on page 75.

To null the electrical offsets:
1.
If the System menu is grayed out, that means no test has been created

since the application was started. Consequently, no nulling can be
performed until you start a new test. For more information, see Starting
a New Test
on page 118.

2. Select Nulling from the System menu of the main window.

3. Put protective caps on power meter detectors as well as on the input

and output of the IQS-9401 WRM as described at the top of the dialog
box.

4. During a nulling, no light should reach the detectors. To avoid

disconnecting the rigid patchcords, click Turn Source Off. The source
and the EDFA will be turned off as soon as you press Start. Once the
nulling is complete, the source is automatically turned on.

5. Click Start to start the null measurement. The Instruction box displays

Nulling in progress.

6. When the operation has been completed, the Instruction box content

changes to Nulling completed. Click Close to return to the main
window.