Loading a fim and its links, Loading a fim and its links -55 – Rockwell Automation PLC-5 Fieldbus Solutions for Integrated Architecture User Manual User Manual
Page 141

Publication 1757-UM006A-EN-P - May 2002
Configurating the 1757-FIM 4-55
Loading a FIM and its Links
The following procedure outlines the typical steps used to “load” a
FIM through the Project tab in Control Builder. It assumes that the FIM
and its associated RTP are installed and capable of communicating
with the system.
1. Verify that the OK LED on the front of the FIM is flashing and
the numbers 1 and 2 are sequencing in the left-hand LED on the
front panel display.
This confirms that the designated FIM is operating and that the
RTP and the H1 segment is OK.
2. Click the FIM block icon in the Project tab.
TIP
If ALIV appears in the FIM’s front panel display, you
must load the FIM’s personality firmware before
proceeding.
This manual is related to the following products: