Switch relay, Power-switch, Activated – SMA Sunny Boy Control User Manual
Page 80: 50kw, Poff, 00kw, Tolerance, 15min, Minimum time, 120min

Sunny Boy Control
SMA Technologie AG
User Manual
SUNBC-14:NE0206
76
Example of a washing machine setup
[ SWITCH RELAY ]
‡Power-switch
…activated
Pon…
…………3.50kW
Switching on if output above 3.5 kW
Poff…
…………2.00kW
Switching off if output below 2.0 kW
Tolerance…
………………15min
Switching on after Pon has been sustained for 15 minutes
Minimum Time…
……………120min
Staying switched on for at least 120 min, even if system power is below Poff
----------------
Time-switch…
…activated
On-time…
………16:00
Switching on at 16:00 (4 PM)
Off-time…
………18:00
Switching off at 18:00 (6 PM)
----------------
Default Switch
…Contact 2_1
Choice between “Contact 2_1” and “Contact 2_2”
Fig. 6.15: Washing machine example
The washing machine will be switched on as soon as the system has produced 3.5
kW (Pon) for at least 15 minutes, and it will remain switched on until the system
power drops below 2 kW (Poff). In any case, the machine will remain switched on
for at least 120 minutes, so that the wash cycle can be completed. If “Pon” (3.5 kW)
could not be reached by 4 PM, the washing machine will anyway be switched on at
4 PM, then switched off at 6 PM.
[ SWITCH RELAY ]
‡Default Switch…
…Contact 2_1
Choice between “Contact 2_1” and “Contact 2_2”
Fig. 6.16: Switching-contact screen