Tool shapes, 7commissioning, 2 initial commissioning – Pilz PSENvip RL D P User Manual
Page 91

Pilz GmbH & Co. KG, Felix-Wankel-Straße 2, 73760 Ostfildern, Germany
Telephone: +49 711 3409-0, Telefax: +49 711 3409-133, E-Mail: [email protected]
7-7
7.2
Initial commissioning
7
Commissioning
7.2.1.5
Tool shapes
Tool shapes
7-
Inbetriebnahme_Erstinbetriebnahme_Empfaenger_ausrichten_Werkzeuge_1
The correct adjustment of the upper tool also depends on the tool
shape. The tools are divided into tool classes in the Tool Change menu.
During initial commissioning, the upper tool should be positioned in a
way that corresponds to the expected tool class.
Two bending lines are available on the PSENvip display for correct align-
ment of the various tool types. In the following examples, please note
that the maximum width of the respective tools for the tool class can be
achieved when the appropriate bending line is used.
Inbetriebnahme_Winkelmessung_Hinweis
Inbetriebnahme_Erstinbetriebnahme_Empfaenger_ausrichten_Werkzeuge_2
INFORMATION
Carefully align the illuminated target area to the receiver. This will
make the adjustments in the following work stages easier.
INFORMATION
You must comply with the tool class information provided in
Section 7.3 "Adjustment during tool change", "Tool detection"
in this chapter.
Section entitled "Tool shapes", under "Safety"
"System Connections" chapter
INFORMATION
The tool must be aligned to the central bending line if bending
angle measurement is to be used.