Visual inspection, 7commissioning, 6 check protective equipment – Pilz PSENvip RL D P User Manual

Page 113: 2 visual inspection

background image

Pilz GmbH & Co. KG, Felix-Wankel-Straße 2, 73760 Ostfildern, Germany
Telephone: +49 711 3409-0, Telefax: +49 711 3409-133, E-Mail: [email protected]

7-29

7.6

Check protective equipment

7

Commissioning

Function test with 10 mm and 15 mm test piece

Position the 10 mm high section of the test piece on top of the lower
tool.

Initiate a press stroke.

Fig. 7-23:

Function test using test piece

The test piece breaks the protected field. The press stroke is stopped.
The upper tool should not touch the test piece.

Once the press stroke has stopped, push the 15 mm high section of
the test piece beneath the upper tool.

The upper tool should not touch the test piece.

Function test using the 35 mm test piece

Start up the press.

Position the 35 mm high section of the test piece on top of the lower
tool.

Initiate a press stroke.

The test piece breaks the protected field. The press stroke is stopped.
The upper tool should not touch the test piece.

7.6.2

Visual inspection

Visual inspection

7-

Inbetriebnahme_Schutzeinrichtung_pruefen_Sichtpruefung

Check the following on the PSENvip transmitter and receiver

The condition of the installation and attachment

Any damage on the housing and lens

Electrical connections

Switch on the machine.

Check the messages on the display.