Page 244: Procedure 20, Verifying successful configuration

244
MG 1000B software installation
—End—
After installing software and configuring basic information about the
Signaling Server, the Signaling Server components can be configured using
the web-based Element Manager interface. See Element Manager System
Reference - Administration (NN43001-632).
Verifying a successful configuration
To ensure that ELAN and TLAN network interfaces on the Signaling Server
are configured correctly, perform a ping test at each interface.
Procedure 20
Verifying successful configuration
Step
Action
1
From the Call Server, in LD 117, enter:
ping
2
From the Media Card, log in to the Media Card and enter:
ping "ip address",3
3
From the Signaling Server, log in and enter:
ping "ip address",3
—End—
Connecting the MG 1000B Core to the network
Connecting the MG 1000B Core to the network
The MG 1000B Core has two 10/100BaseT ports (1 and 2) and one
Attachment Unit Interface (AUI) port at the back on the lower left-hand side.
See
Figure 88 "Back of MG 1000B Core" (page 245)
Nortel Communication Server 1000
Branch Office Installation and Commissioning
NN43001-314