Step
Action
The Front Mount Bracket assembly is not intended for use as a slide rail
system. The Signaling Server must be firmly attached to the rack.
1
Make sure the Signaling Server is not plugged into an electrical
outlet.
2
Align the end of the rail (A in
Figure 75 "Signaling Server brackets
) with the flange (B in
Server support bracket" (page 230)
) toward the back of the Signaling
Server. See
Figure 76 "Signaling Server support bracket" (page
Figure 76
Signaling Server support bracket
3
Align the screw holes in the rack-mount rail with the mating holes in
the side of the Signaling Server. Use three screws (C) on each side.
Hand-tighten the screws to prevent cross-threading then use a
Phillips screwdriver to secure them.
4
Attach the bezel door to the faceplate of the Signaling Server, as
shown in
Figure 77 "Left hinge mount" (page 231)
and
"Right hinge mount" (page 231)
Nortel Communication Server 1000