beautypg.com

Calibrating the series f4, Thermocouple input procedure, Rtd input procedure – Watlow Series F4S/D User Manual

Page 108: Input x (1 to 3) setup and calibration

background image

9 . 2

C a l i b r a t i o n

Wa t l o w S e r i e s F 4 S / D

Thermocouple Input Procedure

Equipment
• Type J reference compensator with reference

junction at 32°F (0°C), or type J thermocouple

calibrator to 32°F (0°C).

• Precision millivolt source, 0 to 50mV minimum

range, 0.002mV resolution.

Input x (1 to 3) Setup and Calibration

1. Connect the correct power supply to terminals

1, 2 and 3 (see the Wiring Chapter and the

Appendix).

2. Connect the millivolt source to Input 1 termi-

nals 62 (-) and 61 (+), Input 2 terminals 58 (-)

and 57 (+), or Input 3 terminals 56 (-) and 55

(+), with copper wire.

3. Enter 50.000mV from the millivolt source. Al-

low at least 10 seconds to stabilize. Press the

Right Key . once at the Calibrate Input x (1

to 3) prompt (Factory Page). At the 50.00mV

prompt press . once and to store 50.00mV

press the Up Key > once.

4. Enter 0.000mV from the millivolt source. Allow

at least 10 seconds to stabilize. At the 0.00mV

prompt press . once and to store 0.00mV

press > once.

5. Disconnect the millivolt source and connect the

reference compensator or thermocouple calibra-

tor to Input 1 terminals 62 (-) and 61 (+) or In-

put 2 or 3 terminals 58 (-) and 57 (+). W ith type

J thermocouple wire, if using a compensator,

turn it on and short the input wires. When us-

ing a type J calibrator, set it to simulate 32°F

(0°C). Allow 10 seconds for the controller to sta-

bilize. Press . once at the Calibrate Input x (1

or 2) prompt (Factory Page). At the 32°F Type J

prompt press . once and to store type J ther-

mocouple calibration press > once.

6. Rewire for operation and verify calibration.

RTD Input Procedure

Equipment
• 1k

decade box with 0.01

resolution.

Input x (1 to 3) Setup and Calibration

1. Connect the correct power supply to terminals

1, 2 and 3 (see the Wiring Chapter and the

Appendix).

2. Short Input 1 terminals 60, 61 and 62; Input 2

terminals 54, 57 and 58; or Input 3 terminals

52, 55 and 56 together with less than 0.1

.

Press the Right Key . once at the Calibrate

Input x (1 to 3) prompt. At the Ground prompt

press . once and to store ground input press

the Up Key > once.

3. Short Input 1 terminals 60 and 61; Input 2 ter-

minals 54 and 57; or Input 3 terminals 52 and

55 together with less than 0.5

. Press . once

at the Calibrate Input x (1 to 3) prompt. At the

Lead prompt press . once and to store lead

resistance press > once.

4. Connect the decade box to Input 1 terminals 60

(S2), 61 (S1) and 62 (S3); Input 2 terminals 54

(S2), 57 (S1) and 58 (S3); or Input 3 terminals

52 (S2), 55 (S1) and 56 (S3), with 20- to 24-

gauge wire.

5. For 100

RTD, enter 15.00

. For 500

or 1k

RTD, enter 240.00

. Allow at least 10 seconds

to stabilize. Press . once at the Calibrate In-

put x (1 to 3) prompt (Factory Page). At the

15.00

or 240.00

* prompt press . once and

to store the 15.00

or 240.00

input press > once.

6. For 100

RTD, enter 380.00

. For 500

or 1k

RTD, enter 6080.00

. Allow at least 10 seconds

to stabilize. Press . once at the Calibrate In-

put x (1 to 3) prompt. At the 380.0

or

6080.00

* prompt press . once and to store

the 380.00

or 6080.00

input press > once.

7. Rewire for operation and verify calibration.

Calibrating the Series F4

NOTE:
You need the equipment listed and technical skills. Con-

trollers come calibrated from the factory. Recalibrate only

for other agency requirements or if temperatures aren’t ac-

curate as verified by another calibrated instrument.

*The tenth character of your model number determines

what prompts appear and what input resistance values to

use for the RTD calibration.

F4_ _-_ _ _ _-_(1 to 4)

RG

: 15.00 and 380.00

F4_ _-_ _ _ _-_(5 to 8)

RG

: 240.00 and 6080.00