☐ The ground resistance of the PV system must have been determined.

☐ All values measured must be within the permissible range.

Procedure:

1. Lock the inverter.

2. Turn the key switch to Start.

☑ The DC switch switches on with an audible click.

☑ Under conditions of sufficient irradiation, the inverter starts feeding into the utility grid.

✖ Disturbance message on the touch display?

• Eliminate the disturbance (see Section 7, page 65).