☐ The ground resistance of the PV system must have been determined.
☐ All values measured must be within the permissible range.
Procedure:
1. Lock the inverter.
2. Turn the key switch to Start.
☑ The DC switch switches on with an audible click.
☑ Under conditions of sufficient irradiation, the inverter starts feeding into the utility grid.
✖ Disturbance message on the touch display?
• Eliminate the disturbance (see Section 7, page 65).
4 Commissioning
SMA Solar Technology AG
User Manual
SCCPXT-BA-E4-en-54
50
This manual is related to the following products:
- SC 630CP XT SC 720CP XT SC 760CP XT SC 800CP XT SC 850CP XT SC 900CP XT SC 500CP XT Maintenance Manual SC 630CP XT Maintenance Manual SC 720CP XT Maintenance Manual SC 760CP XT Maintenance Manual SC 800CP XT Maintenance Manual SC 850CP XT Maintenance Manual SC 900CP XT Maintenance Manual SC 1000CP XT SC 1000CP XT Maintenance Manual