7 changing the communication period – SMA SC 500CP XT User Manual
Page 43
5. Select the tab Instantaneous values.
6. Select SSMUNoOf and check the number of detected Sunny String-Monitors.
If only some of the Sunny String‑Monitors have been detected, use Sunny Central String‑Monitor Controller to
redetect them (see Section 4.6.10.4, page 43).
4.6.10.4 Redetecting the Sunny String-Monitors via the Sunny Central String-
Monitor Controller
1. Log into the user interface (see Section 9.4.1, page 81).
2. Select the tab Parameters.
3. Set the parameter DevFunc to Retry.
4. Select the button [Save].
5. Select the tab Instantaneous values.
6. Select SSMUNoOf and check the number of detected Sunny String-Monitors.
If only some of the Sunny String-Monitors have been detected, contact the Service .
4.6.10.5 Detecting the Sunny String-Monitors via the Communication Unit
1. Log into the user interface (see Section 9.4.1, page 81).
2. Select Data > Detection.
3. In the field Total number of devices to be detected, enter the number of Sunny String-Monitors +2.
4. Select the button [Start detection].
☑ The communication unit starts detecting all inverters and displays its progress. Once all devices have been
detected, the message ### Device detection finished ### is displayed.
☑ The Sunny String-Monitors have been detected.
4.6.10.6 Adjusting the Identification of the Sunny String-Monitors
1. Log into the user interface (see Section 9.4.1, page 81).
2. Select the first Sunny String-Monitor from the device list.
3. Select the tab Parameters.
4. Select the parameter SSMId and allocate a unique identification number to the Sunny String-Monitor. Note the
identification number.
5. Adjust the identification of the remaining Sunny String-Monitors using the same process.
4.6.10.7 Changing the Communication Period
The communication period is the time for which the Sunny Central String-Monitor Controller communicates with the
Sunny String-Monitors. The communication period is set from 10:00 a.m. to 3:00 p.m. by default.
Procedure:
1. Log into the user interface (see Section 9.4.1, page 81).
2. Select the parameter MoniTmComOn and set the start of the communication period.
3. Select the parameter MoniTmComOff and set the end of the communication period.
4. Select the button [Save].
4 Commissioning
SMA Solar Technology AG
User Manual
43
SCCPXT-BA-E4-en-54
- SC 630CP XT SC 720CP XT SC 760CP XT SC 800CP XT SC 850CP XT SC 900CP XT SC 500CP XT Maintenance Manual SC 630CP XT Maintenance Manual SC 720CP XT Maintenance Manual SC 760CP XT Maintenance Manual SC 800CP XT Maintenance Manual SC 850CP XT Maintenance Manual SC 900CP XT Maintenance Manual SC 1000CP XT SC 1000CP XT Maintenance Manual