SMA SC 500CP XT User Manual
Page 111
Depending on the order option, the inverter may be equipped with a managed switch.
Figure 38: System network of two inverters (example)
Monitoring and control can be organized in two separate networks:
• Monitoring network
This network is used for monitoring, parameterization and remote diagnosis.
• Control network
The grid operator uses this network to transmit grid management specifications to the inverters. The control
network is used exclusively for grid management services that need to be transmitted and implemented within a
specified time period.
If only a low data transfer rate is required for monitoring, grid operator specifications can also be transmitted via the
monitoring network. Only one network is required in this case.
10 Function Description
SMA Solar Technology AG
User Manual
111
SCCPXT-BA-E4-en-54
- SC 630CP XT SC 720CP XT SC 760CP XT SC 800CP XT SC 850CP XT SC 900CP XT SC 500CP XT Maintenance Manual SC 630CP XT Maintenance Manual SC 720CP XT Maintenance Manual SC 760CP XT Maintenance Manual SC 800CP XT Maintenance Manual SC 850CP XT Maintenance Manual SC 900CP XT Maintenance Manual SC 1000CP XT SC 1000CP XT Maintenance Manual