3 visual inspection and mechanical test, Visual inspection and mechanical test, Sequence for visual inspection and mechanical test – SMA SC 500CP XT User Manual

Page 29

background image

☐ All doors and locks must function properly.

☐ All documentation must be available.

☐ All labels must be in place.

4.3

Visual Inspection and Mechanical Test

4.3.1

Sequence for Visual Inspection and Mechanical Test

Procedure

See

1.

Ensure that the minimum clearances are complied with.

Section 12.1.1, page 146

2.

Ensure that the grounding busbar has been professionally connected to the external grounding system.

3.

Ensure that the cables for communication, control, supply voltage and
monitoring are correctly connected.

Section 4.3.2, page 29

4.

Ensure that the high-current contacts made on the installation site are cor-
rectly connected.

Section 4.3.3, page 30

5.

Ensure that the high-current contacts made at the factory are correctly
connected.

Section 4.3.4, page 30

6.

Ensure that the connection busbars do not show any discoloration.

If the connection busbars show any discoloration, please contact us (see Section 13 "Contact", page 154).

7.

Ensure that the settings of the switching units are made correctly.

Section 4.3.5, page 30

8.

Ensure that all connectors are correctly connected.

Section 4.3.6, page 31

4.3.2

Checking the Connections of the Cables for Communication, Control
Supply Voltage and Monitoring

Test Point

Tasks

Cables

Ensure that the cable type and cross-section, the number of cables and the labeling comply
with the specifications in the schematic diagram.

Cable connection

Ensure that the cable connection complies with the specifications in the schematic diagram.

If no external fast stop is to be installed, ensure that the terminals are wired with a jumper
wire in accordance with the schematic diagram.

Cable insulation

Make sure that the insulation of the cables is correctly stripped. The insulation must not pre-
vent the contact with the terminal.

Bootlace ferrules

Ensure that the bootlace ferrules are correctly crimped and that no stranded wires are visible.

Cable support rails

Ensure that the cables are adequately attached to the cable support rails.

Shield clamping sad-
dles

Ensure that the contact between the cable shield and the shield bus is intact.

4 Commissioning