beautypg.com

4 commissioning, 1 safety during commissioning, 2 requirements for commissioning – SMA SC 500CP XT User Manual

Page 28: Commissioning, Safety during commissioning, Requirements for commissioning, 4commissioning

background image

4

Commissioning

4.1

Safety during Commissioning

Danger to life from electric shock due to live voltage

High voltages are present in the live components of the product. Touching live components results in death or serious
injury due to electric shock.

• Wear suitable personal protective equipment for all work on the product.

• Do not touch any live components.

• Observe all warning messages on the product and in the documentation.

• Observe all safety information of the module manufacturer.

• After switching off the inverter, wait at least 15 minutes before opening it to allow the capacitors to discharge

completely (see Section 5.2, page 51).

Danger to life from electric shock due to ground fault

If a ground fault has occurred, parts of the PV power plant that are supposedly grounded may in fact be live.
Touching incorrectly grounded parts of the PV power plant results in death or serious injuries from electric shock.

• Before working on the PV power plant, ensure that no ground fault is present.

• Wear suitable personal protective equipment for all work on the device.

Property damage due to dust intrusion and moisture penetration

Dust or moisture intrusion can damage the product and impair its functionality.

• Do not open the enclosure during rainfall or when humidity exceeds the specified thresholds. The humidity

thresholds are: 15 % … 95 %.

• Only perform maintenance work when the environment is dry and free of dust.

• Operation of the product is only permitted when it is closed.

• Connect the external supply voltage after mounting and installing the product.

• If the installation or commissioning process is interrupted, mount all panels.

• Close and lock the enclosure.

• The product must always be closed for storage.

• Store the product in a dry and covered location.

• Temperature at the storage location must be in the specified range. The temperature range is: −25°C to +70°C

.

4.2

Requirements for Commissioning

☐ None of the devices must display any damage.

☐ All devices must be correctly installed.

☐ All devices must be properly grounded.

☐ All transport locks and desiccant bags must be removed.

☐ All cables of the inverters must be correctly routed and connected.

4 Commissioning

SMA Solar Technology AG

User Manual

SCCPXT-BA-E4-en-54

28