Powerflex “c” frame commissioning checklist – Rockwell Automation 7000L PowerFlex Medium Voltage AC Drive (C Frame) - Classic Control User Manual
Page 217
4-12
Commissioning
7000L-UM300I-EN-P – June 2013
7000 “C” Frame
PowerFlex “C” Frame Commissioning Checklist
Programming the Operator Interface
Verify preliminary parameter settings.
Calibrate signal conditioners
Set analog outputs
Fault masks / External faults
Analog I/O
PLC In/Out
System Tests
Perform a system test with low voltage control/test power.
Prove all protection functions as desired.
Verify that all emergency stop devices function.
Calibrate the analog I/O.
Test cooling system operation.
Medium Voltage
Tests
Pre-Power Tests
Inspect cabinets for debris (tools, hardware, metal shavings, etc.).
Re-install control fuses (to be done with control power off).
Power Tests
Measure input contactor drop out time. (2-cycle advance warning
needed if input contactor is not part of drive line-up)
Verify that line voltage is at rated value.
Verify harmonic by checking voltage and current waveforms at SCBL
board (PWM only).
Perform a phasing check (18-pulse drives only).
Review drive program settings for operating at reduced load.
Perform an IDC Test.
Autotune
Program the drive for operation at full load.
Run drive at rated load and rated speed.
Capture waveforms of voltages and currents on the line and motor sides.
Paperwork
Print DRIVE SETUP, which gives all parameters, firmware revisions,
PLC links, etc.
Complete the Commissioning Data Sheets.
Mark up modified electrical drawings.
Add revision notes to modified PLC program.
Have the customer sign sign-off document.
Provide customer with parameter settings, marked-up drawings,
commissioning package, PLC program and Field Report.
Forward PLC program, modified drawings, Commissioning Package
and Field report to Medium Voltage Support group.