beautypg.com

Powerflex “c” frame pre-commissioning checklist – Rockwell Automation 7000L PowerFlex Medium Voltage AC Drive (C Frame) - Classic Control User Manual

Page 209

background image

4-4

Commissioning

7000L-UM300I-EN-P – June 2013

7000 “C” Frame

Please print the following information:





PowerFlex “C” Frame Pre-Commissioning Checklist


Once all points of the checklist are complete, initial each check box and provide the date. Photocopy the
checklist and fax the copy to the Medium Voltage Center of Expertise (MV COE) along with the planned
start-up date. Upon receiving this checklist, the MV COE will contact the site to finalize arrangements for
a start-up engineer to travel to site if so desired by the end user.

Drive Serial Number:

GMS Service Engineer Requested (YES/NO):

Scheduled Commissioning Date:

1. Receiving and Unpacking

Initials Date

The drives have been checked for shipping damage upon receiving.

After unpacking, the item(s) received are verified against the bill of
materials.

Any claims for breakage or damage, whether concealed or obvious,
are made to the carrier by the customer as soon as possible after
receipt of shipment.

All packing material, wedges, or braces are removed from the
drive.

2. Installation / Mounting

Initials Date

The drive is securely fastened in an upright position, on a level
surface. Seismic zones require special fastenings. Consult factory.

Lifting Angles have been removed.

Bolts have been inserted into original location on top of drive
(leakage of cooling air).

All contactors and relays have been operated manually to verify
free movement.

Medium Voltage– Center of Expertise

Rockwell Automation

Fax: 1 (866) 465-0103 or

Fax: 1(519) 740-4756

Name:

Company:

Phone:

Fax:

Date:

Pages: