beautypg.com

Commissioning, Chapter – Rockwell Automation 7000L PowerFlex Medium Voltage AC Drive (C Frame) - Classic Control User Manual

Page 206

background image

Chapter

4

7000 “C” Frame

7000L-UM300I-EN-P – June 2013


Commissioning


Start-up will be performed at the customer's site. Rockwell
Automation requests a minimum of four (4) weeks‟ notice to
schedule each start-up.


The standard Rockwell Automation work hours are between 8:00
AM to 5:00 PM EST, (8 hr/day) Monday through Friday, not
including observed holidays. Additional working hours are available
on a time and material basis.


Rockwell Automation recommends the following:

Drive Commissioning


1.

A pre-installation meeting with the customer to review:

– The Rockwell Automation Start-up Plan

– The Start-up Schedule

– The Drive(s) installation requirements

2.

Inspect the drive‟s mechanical and electrical devices.

3.

Perform a tug test on all internal connections within the drive

and verify wiring.

4.

Verify critical mechanical connections for proper torque

requirements.

5.

Verify and adjust mechanical interlocks for permanent

location.

6.

Confirm all inter-sectional wiring is connected properly.

7.

Re-verify control wiring from any external control devices

such as PLC5.

8.

Confirm cooling system is operational.

9.

Verification of proper phasing from input voltage source to

drive.

10.

Confirm cabling of drive to motor, isolation transformer and

line feed.

11.

Collect test reports indicating megger / hipot test has been
performed on line and motor cables.

12.

Control power checks to verify all system inputs such as
starts/stops, faults, and other remote inputs.

Start-up Commissioning

Services