6 commissioning, 1 before you start, Commissioning – Lenze ECSCMxxx User Manual
Page 92: Before you start

Commissioning
Before you start
6
l
92
EDBCSXM064 EN 11.0
6
Commissioning
6.1
Before you start
)
Note!
ƒ
The use of a Lenze motor is assumed in this description of the
commissioning steps. For details on the operation with other motors see
^ 174.
ƒ
The operation with the Lenze parameter setting and operating program
"Global Drive Control (GDC)" is taken as a basis. The parameters are
displayed in the online mode, i.e. GDC can directly access the codes of the
axis module.
Prior to initial switch−on of the drive system, check the wiring for completeness,
short−circuit, and earth fault:
ƒ
Power connection:
– Polarity of the DC−bus voltage supply via terminals +UG, −UG
ƒ
Motor connection:
– In−phase connection to the motor (direction of rotation)
ƒ
Wiring of "safe torque off" (formerly "safe standstill")
ƒ
Feedback system
ƒ
Control terminals:
– Wiring adjusted to the signal assignment of the control terminals.