Installing the chassis in an equipment rack, Required tools and material, Preparing the equipment rack – Allied Telesis SwitchBlade x3106 User Manual
Page 83

SwitchBlade x3106 Installation Guide
83
Installing the Chassis in an Equipment Rack
The following sections contain the procedures for installing the unit in an
equipment rack:
“Required Tools and Material” on page 83
“Preparing the Equipment Rack” on page 83
“Removing the Rubber Feet” on page 85
“Adjusting the Equipment Rack Brackets” on page 86
“Installing the Chassis in the Equipment Rack” on page 89
Required Tools
and Material
You need the following tools and material to install the product in an
equipment rack:
#2 Phillips-head screwdriver
Six equipment rack screws
Flat-head screwdriver
#2 Phillips-head 10 inch-lbs torque screwdriver (optional)
Warning
The chassis may be heavy and awkward to lift. Allied Telesis
recommends that you get assistance when mounting the chassis in
an equipment rack. E30
Preparing the
Equipment Rack
To prepare the equipment rack for the installation of the AT-SBx3106
Chassis, perform the following procedure:
Caution
The chassis is heavy and should be mounted as low as possible in
the equipment rack to maximize vertical stability.
1. Reserve 190.0 mm (7.5“) of vertical rack space for the installation of
the AT-SBx3106 Chassis, as shown in Figure 36 on page 84.
2. Do not mount any other equipment within 152.4 mm (6”) above this
space during installation. This additional vertical space is temporary
and allows you enough room to lift and tilt the chassis into its position
in the equipment rack without hitting other equipment, as shown in
Figure 42 on page 90. You may use this additional space for other
network equipment after the chassis is installed.