4.2

Sequence of Steps from Choosing to Commissioning

the Digital Module

Introduction

The following table contains the tasks that you have to perform one after the other
to commission digital modules successfully.

The sequence of steps is a suggestion, but you can perform individual steps either
earlier or later (for example, assign parameters to the module) or install other
modules or install, commission etc. other modules in between times.

Sequence of Steps

Table 4-4

Sequence of Steps from Choosing to Commissioning the Digital Module

Step

Procedure

Refer To...

1.

Select the module

Section 4.1 and specific module section from
Section 4.8

2.

Install the module in the SIMATIC S7
network

“Installation” section in the manual for the
programmable controller being used:

S7-400/M7-400 Programmable Controllers,
Hardware and Installation

3.

Assign parameters to module

Section 4.3 and, if necessary, the specific module
section as of Section 4.7

4.

Commission configuration

Section on commissioning in the manual for the
programmable controller being used:

S7-400/M7-400 Programmable Controllers,
Hardware and Installation

5.

If commissioning was not successful,
diagnose configuration

Section 4.4