4. Commissioning
4-33
Festo P.BE-SPC11-SYS-EN en 1406e
Overview of the commissioning sequence on the
SPC11
Set the parameters and start the automatic teach procedure
(SPC11 in status at delivery)
Switch on
Set (only for SPC11-INC):
- Nominal stroke length (L)
- Offset axes zero point (r)
Setting:
- Amplification stage (A)
- Cushioning stage (C)
- System parameters (S)
Set respective
value with +/-.
Conclude each
entry with Enter.
The SPC11 waits for
the teach task
Pre-commissioning
is concluded.
Teach task can be
started.
Teach procedure is
carried out
The teach task is concluded successfully
Mass is pressed against
the end position;
O1 supplies a 1-signal
P.03 and P.04 can be
taught (see next page).
The t flashes
The dots flash
Enter button
Teach button/input
Firmware version number
Display of
firmware version
Wait approx. 0.5 second
Setting (optional)
- o-parameter
Fig. 4/5: Setting the param. and starting the teach procedure