Grass Valley PDR 200 Service Manual User Manual
Page 77

Executing Test All Boards
PDR200 Service Manual
4-27
• The Test Status box opens on top of the panel on the left. See Figure 4-8 for an
example.
Figure 4-8. Test Status Box
This box consists of:
-
Test:
Identifies the test in progress.
-
Pass:
How many times the test has been run, cannot exceed number in the
Of:
field, which was set in Preferences box.
-
Time:
How long the test in progress has been running.
-
Warnings:
The number of times, if any, a test parameter was exceeded.
-
Errors:
The number of errors, if any, which occurred during testing. (This
depends on options selected in the Preferences box.)
-
Status:
Running appears here during test execution. If no errors were detected,
PASSED
appears and if an error occurred,
FAILED
appears.
-
Cancel
button which, if selected, terminates all testing at the completion of
testing the current board. (If testing an individual board, testing terminates at
the completion of the test in progress.)
• Simultaneously with the above, the lower right system report and information
panel, partially hidden by the GDB960 window, initially shows the loading of the
diagnostics program ID data. As a test begins, both the lower right panel of the
Diagnostics window and the GDB960 window show the test being run and the test
results (i.e., Passed or Failed).