2.4.5 S0–S3 Bank DIP Switches to Select and Load Device Configuration Files
The “S” Bank of DIP switches (S0 - S3) is used to select and load a configuration file from a
group of pretested/preloaded configuration files, which are stored in the ProtoNode RER
FPC-N34 (BACnet MS/TP, BACnet/IP, Modbus TCP, Metasys N2) and the ProtoNode LER
FPC-N35 (LonWorks).
Figure 2-4: S0-S3 DIP Switch Locations
2.4.5.1 ProtoNode RER S0 to S3 (and A1& A3) DIP Switch Settings
The “A1” and “A3” switches listed in the chart below refer to the additional Mini DIP switches,
NOT the “A” Bank DIP switches (A0 – A7) that are accessible with the cover on. To access
the Mini DIP switches you must remove the cover, as shown in Figure 2-5.
Except for those listed below, all other Mini DIP switches are in the
Off
position.
TABLE 2-4: ProtoNode RER S0 to S3 (and A1*) DIP Switch Settings
S0 S1 S2 S3 A1
Profile
Off
Off
Off
Off
Off
BACnet/IP/BACnet MS/TP, 1 ACS/BMS II, 4 C-More Controlled Boilers
ON
Off
Off
Off
Off
BACnet/IP/BACnet MS/TP, 1 ACS/BMS II, 8 C-More Controlled Boilers
Off
ON
Off
Off
Off
BACnet/IP/BACnet MS/TP, 1 ACS/BMS II, 12 C-More Controlled Boilers
ON ON
Off
Off
Off
BACnet/IP/BACnet MS/TP, 1 ACS/BMS II, 4 Modulex Boilers With BCMs
Off
Off
ON
Off
Off
BACnet/IP/BACnet MS/TP, 4 ECS/SP Systems
ON
Off
ON
Off
Off
BACnet/IP/BACnet MS/TP, 12 C-More, 6 ECS/SP, 4 Modulex and 2 ACS/BMS II
Off
ON ON
Off
Off
Metasys N2, 1 ACS/BMS II, 4 C-More Controlled Boilers
ON ON ON
Off
Off
Metasys N2, 1 ACS/BMS II, 8 C-More Controlled Boilers
Off
Off
Off
ON
Off
Metasys N2, 1 ACS/BMS II CS, 12 C-More Controlled Boilers
ON
Off
Off
ON
Off
Metasys N2, 1 ACS/BMS II, 4 Modulex Boilers with BCMs
Off
ON
Off
ON
Off
Metasys N2, 4 ECS/SP Systems
ON ON
Off
ON
Off
Metasys N2, 12 C-More, 6 ECS/SP, 4 Modulex and 2 ACS/BMS II
Off
Off
ON ON
Off
Modbus TCP, 1 ACS/BMS II, 4 C-More Controlled Boilers
ON
Off
ON ON
Off
Modbus TCP, 1 ACS/BMS II, 8 C-More Controlled Boilers
Off
ON ON ON
Off
Modbus TCP, 1 ACS/BMS II, 12 C-More Controlled Boilers
ON
ON ON ON
Off
Modbus TCP, 1 ACS/BMS II, 4 Modulex Boilers With BCMs
Off
Off
Off
Off
ON
Modbus TCP, 4 ECS/SP Systems
ON
Off
Off
Off
ON
Modbus TCP, 12 C-More, 6 ECS/SP, 4 Modulex and 2 ACS/BMS II
S0 S1 S2 S3 A1 A3
Profile
ON
Off
Off
Off
Off
ON
Slave/Slave Device (SSD) Modbus – for WHM and BST systems
Off
ON
Off
Off
Off
ON
Slave/Slave Device (SSD) Bacnet – for WHM and BST systems
ON
ON
Off
Off
Off
ON
Slave/Slave Device (SSD) N2 – for WHM and BST systems
S0 – S3 DIP
Switches
S Bank DIP
Switch
Location
A Bank DIP
Switch
Location
Mini DIP
Switches
Located
Under
Cover
S0 S1 S2 S3