Site Configuration and Overall Equipment Efficiency (OEE)
When you first create your company in CheckPoint™, the first level on the Welders tab is the Company Site.
Configuring your site’s Idle Time Threshold, Planned Arc Time Per Hour and Planned Downtime allows
CheckPoint™ to calculate your OEE values accurately. Table 4.2 explains the Site Definition section. Please
refer to Chapter 9 for in-depth details on OEE and how to establish your plant’s Planned Downtime.
Figure 4.19 Configuring Your Company Site
Table 4.2
Fields in the Site Definition Section
Field
Description
Name
This is the name of the Company Site as it appears in the Asset Tree in the
main CheckPoint™ application.
Idle Time Threshold
This is the amount of time that all machines under this Company Site can
be idle before the lapse in productivity begins to be counted as
Unplanned Downtime. Please see page 9.8 for more details on
Unplanned Downtime.
Planned Arc Time Per Hour
Enter the amount of time that you expect every machine under this
Container to be welding. This value is used for OEE calculations. Please
see page 9.8 for more details on the Performance factor of OEE.