beautypg.com

Lincoln Electric IM8000 CHECKPOINT User Manual

Page 30

background image

Chapter 2. Preparing for CheckPoint™

Enable CheckPoint™ for a Power Source

2.8 CheckPoint™

User

Manual

IM8000

Enabling CheckPoint™

Once you connect the Welding Power Source to Power Wave® Manager, you can now enable and set up
CheckPoint™ for that power source. Once you enable CheckPoint™ for the power source, the CheckPoint™
administrator will be able to begin adding Welding Power Sources to the CheckPoint™ system for
monitoring and reporting.

Figure 2.2 Registration Section of Power Wave® Manager

Procedure

Details

1.

Select

Register under Production Monitoring

in Power Wave® Manager.

2.

Enter a name for the Welding Power Source

in the Power Source name field.

If you do not see this section, the firmware on the
connected Welding Power Source is not up to date.
Please refer to page 2.1 to update the firmware of
the power source. Return here when complete.

3.

Place a check mark in the Enable

CheckPoint™ over the Internet checkbox
under CheckPoint™ Setup.

Once you enable CheckPoint™ for the power source,
the Welding Power Source no longer sends e-mail
notifications. With CheckPoint™, e-mail and text
message notifications come from the data center.