Execution/setup, Calibration, Indication check – Yokogawa Multi Channel Oxygen Analyzer System ZR22/AV550G User Manual
Page 107: Blow back
IM 11M12D01-01E
6-9
6. Components
4) Execution/Setup display
Touch the Setup key on the basic panel display. The Execution/Setup display will
appear. From the menu items — calibration, indication check, blow back, maintenance,
or commissioning, select the desired item to perform.
Enter
Execution/Setup
Calibration
᭜
Indication check
᭜
Blow back
Setup
᭜
Maintenance
᭜
Commissioning
F06E.EPS
Execution
Figure 6.10 Execution/Setup Display
5) Calibration display
From the menu on the Execution/Setup display, select Calibration. The Calibration
display will appear. Calibration can be performed from the menu on this display.
Enter
Manual calibration
᭜
Semi-auto calibration
F07E.EPS
Calibration
Figure 6.11 Calibration Display
6) Indication check display
From the menu on the Execution/Setup display, select Indication Check. The Indication
Check display will appear. Indication check can be performed from the menu on this
display.
7) Blow back display
From the menu on the Execution/Setup display, select Blow back. The Blow back
display will appear. Blow back can be performed from the menu on this display.
Enter
Manual ind. check
᭜
Semi-auto ind. check
F08E.EPS
Indication check
Enter
Start blow back
᭜
Cancel blow back
F09E.EPS
Blow back
Figure 6.12 Indication Check Display Figure 6.13 Blow Back Display