Wiring AC Power

Revision E

Power

2-3

W

IRING

AC P

OWER

DANGER

!

Turn off AC power at the source (circuit breaker panel) before accessing the wires in the Swing-
Smart junction box. Follow facility Lock Out/Tag Out procedures. Make sure both the DC and AC
power switches, on the side of the SwingSmart control box are in the off position. See Figure 2-2.

CAUTION

!

Wiring of gate operators must conform to the NEC standards and comply with all local codes.
If you plan to connect to 208/230VAC power, read the WARNING in Figure 2-2. The voltage
selector switch on the AC Power board must be moved to the 230V position or damage to the
operator will occur and void the Limited Warranty.

Figure 2-2.

WARNING

Place the power switches in the
OFF position.

Service outlet

115 VAC wires for the service outlet.

Junction box cover and label

Voltage selector switch is
factory set to 115V.

If power input is 208/230V,

move the switch so 230V

appears and change the

label on the junction

box cover.

The service outlet is wired for 115VAC. To
use the 115VAC service outlet on a 208/
230VAC installation, the electrician needs
to run an extra neutral wire to the operator
from the power source and wire the service
outlet per code.

High voltage
protection cover.

NOTE: For 208VAC a separate transformer option
kit may need to be ordered.