Installation Guideline


2-10 ADAM 4000 Series User’s Manual

• Power on all components except the ADAM Module.
• Power the ADAM module on while shorting the INIT* and GND

terminals (See Figure 2-3) or set the INIT switch to “Init” (See
Figure 2-4)

Figure 2-3 Grounding the INIT* Terminal

Figure 2-4 Set INIT switch to “Init”


• Configure the checksum status and/or the baud rate.
• Switch the power OFF to the ADAM Module.
• Remove the grounding of the INIT* terminal and turn on the

module, or set the INIT switch to “Normal”.

• Check the settings (If the baud rate has changed, the settings on the