Attach third cross deck support channel to decking – Grain Systems Bucket Elevtors, Conveyors, Series II Sweeps PNEG-1849 User Manual
Page 73

9. 30"-36" Head Platform Left Hand Drive
PNEG-1849 30"-36" Bucket Elevator Platform and Ladder “X” Series
73
Attach Third Cross Deck Support Channel to Decking
NOTE: Connect all bolts only finger tight until deck is completely assembled and then tighten to
proper torque.
1. Locate the third (3
rd
) cross deck support channel (HP36DSCX) and orient it so the X side faces up
and hole X1 is on the non-drive side of the lower head assembly.
2. Align holes. Use a punch as needed to align holes accordingly:
a. At the drive side - Channel hole X7 on the cross deck support channel to Deck F hole F6.
b. At the hatch side - Channel hole X2 on the cross deck support channel to Deck A hole A10 and
c. Connect Deck F to support channels using 3/8" x 1" carriage bolts (S-3585) with flange nuts
(S-10028). Connect all holes between channel and deck.
Attach Deck E to Deck A, Deck C and Cross Deck Support Channel
NOTE: Connect all bolts only finger tight until deck is completely assembled and then tighten to
proper torque.
1. Position Deck E between Deck A and Deck C. Note that Deck E will be connected to two (2)
channels.
2. Align holes. Use a punch as needed to align deck holes E5 with channel hole X3. This will align Deck
3. Connect Deck E to cross deck support channels using 3/8" x 1" carriage bolts (S-3585) with flange
nuts (S-10028). Connect all holes between channels and deck.
4. Connect the Deck E kick plate flanges to toe boards and flanges of Deck A and Deck C using
3/8" x 3/4" bolts (S-7105) and 3/8" nuts (S-10028).
5. Align and connect Deck E to Deck A and Deck C using 3/8" x 1" bolts (S-7469) with flange nuts
(S-10028).
a. C Deck hole C12 to E deck hole E1.
b. C Deck hole C9 to E deck hole E2.
c. A Deck hole A13 to E deck hole E3.
d. A Deck hole A11 to E deck hole E4.