HP Insight Control User Manual
Page 128

7.
Test the network connections and latency between the source-to-destination server and the
application-station-to-destination server. The results of a 2-second test initially appear.
8.
To perform additional tests, select a test time in the Test network connections section, and then click
Test
. The following test times are available:
•
2 seconds
•
5 seconds
•
10 seconds
•
30 seconds
•
60 seconds
If you cannot establish the source-to-destination or application-station-to-destination connection, the Next
button is disabled. Ensure that ports 51125 and 51126 are open between source and destination
servers.
If you establish the source-to-destination or application-station-to-destination connection but the network
test reports a transfer speed below 250 kb/s, the Next button is disabled.
If you establish the source-to-destination or application-station-to-destination connection and the network
test reports a transfer speed of at least 250 kb/s, the Next button is enabled.
CAUTION:
If the application-station-to-destination latency is less than 125 milliseconds, continue with
the migration. Latency greater than 125 milliseconds might cause driver injection issues.
9.
Click Next.
128
Using Insight Control server migration to migrate servers