Insight Control disables the Next and Previous buttons during the reboot. To view the booting process
of the destination server, click Launch iLO, and then open the remote console.
To cancel the boot process and power down the destination server, click Cancel Booting, then click
Next
.
7.
Test the network connections and latency between the source-to-destination server and the
application-station-to-destination server. The results of a 2-second test initially appear.
8.
To perform additional tests, select a test time in the Test network connections section, and then click
Test
. The following test times are available:
•
2 seconds
•
5 seconds
•
10 seconds
•
30 seconds
•
60 seconds
If you cannot establish the source-to-destination or application-station-to-destination connection, the Next
button is disabled. Ensure that ports 51125 and 51126 are open between source and destination
servers.
If you establish the source-to-destination or application-station-to-destination connection but the network
test reports a transfer speed below 250 kb/s, the Next button is disabled.