beautypg.com

9 ssov proof of closure switch – AERCO BMK 2000DF User Manual

Page 87

background image

Benchmark 1500DF - 2000DF Boilers

CHAPTER 6 – SAFETY DEVICE TESTING

OMM-0098_0A

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913

Page 87 of 196

GF-144

Ph.: 800-526-0288

04/01/2014

Figure 6-4: Boiler Rear View Showing Air Inlet Location

6.9 SSOV PROOF OF CLOSURE SWITCH

The SSOV shown in Figure 6-1 contains the proof of closure switch. The proof of closure switch

circuit is checked as follows:

SSOV Proof of Closure Switch

1. Set the unit’s ON/OFF switch to the OFF position.
2. Place the unit in Manual Mode and set the valve position between 25% and 30%
3. Refer to Figure 6-1 and locate the SSOV.
4. Remove the cover from the SSOV by loosening the screw shown in Figure 6-5. Lift off the

cover to access the terminal wiring connections.

5. Disconnect wire #148 from the SSOV to “open” the proof of closure switch circuit.
6. The unit should fault and display SSOV SWITCH OPEN.
7. Replace wire #148 and press the CLEAR button.
8. Set the ON/OFF switch to the ON position to start the unit.
9. Remove the wire again when the unit reaches the purge cycle and PURGING is

displayed.

10. The unit should shut down and display SSOV FAULT DURING PURGE.
11. Replace the wire on the SSOV and press the CLEAR button. The unit should restart.

AIR INLET

PRIMARY

WATER INLET

DRAIN VALVE

ANALYZER

PORT

EXHAST

MANIFOLD

CONDENSATE DRAIN

This manual is related to the following products: