Figure 2-2: Boiler Lifting Provisions


In multiple unit installations, it is important to plan the position of each unit in advance. Sufficient

space for piping connections and future service/maintenance requirements must also be taken

into consideration. All piping must include ample provisions for expansion.
If installing a Combination Control Panel (CCP) system, it is important to identify the

Combination Mode Boilers in advance and place them in the proper physical location. Refer to

Chapter 5 for information on Combination Mode Boilers.












LIFTING LUGS

(3 POSITIONS)

2” NATURAL

GAS INLET

1” PROPANE

INLET