4.3 NATURAL GAS COMBUSTION CALIBRATION
The Benchmark boiler is combustion calibrated at the factory prior to shipping. This gas
pressure must be within the following ranges for each model of boiler at full fire:
Table 4-1: Nominal Gas Pressure – NATURAL GAS
BMK Boiler Model
Nominal Gas Pressure
BMK 1500DF
3.5” W.C. ±0.2” W.C.
BMK 2000DF
6.3” W.C. ±0.2” W.C.
Recalibration as part of initial start-up is necessary due to changes in the local altitude, gas BTU
content, gas supply piping and supply regulators. Combustion Calibration Test Data sheets are
shipped with each unit. These sheets must be filled out and returned to AERCO for proper
Warranty Validation.
It is important to perform the following procedure as outlined. This will keep readjustments to a
minimum and provide optimum performance.
The following Instructions for NATURAL GAS combustion calibration apply to both BMK
1500DF and BMK 2000DF model units.
NATURAL GAS Combustion Calibration
1. Open the water supply and return valves to the unit and ensure that the system pumps
are running.
2. Open the natural gas supply valve to the unit.
3. Set the control panel ON/OFF switch to the OFF position
4. Turn on external ac power to the unit. The display will show loss of power and the time
and date.
5. Set the unit to the manual mode by pressing the AUTO/MAN key. A flashing manual
valve position message will be displayed with the present position in %. Also, the
MANUAL
LED will light.
6. Adjust the air/fuel valve position to 0% by pressing the ▼ arrow key.
7. Ensure that the leak detection ball valve downstream of the SSOV is open.
8. Set the ON/OFF switch to the ON position.
9. Change the valve position to 30% using the ▲ arrow key. The unit should begin its start
sequence and fire.
10. Next, verify that the gas pressure downstream of the SSOV is set to the proper value,
listed in Table 4-1. If gas pressure adjustment is required, remove the brass hex nut on
the SSOV actuator to access the gas pressure adjustment screw (Figure 4-3). Make gas
pressure adjustments using a flat-tip screwdriver to obtain the proper gas pressure.
11. Using the ▲ arrow key, increase the valve open position to 100%. Verify that the gas
pressure on the downstream side of the SSOV settles within the range listed in Table 4-1.
Readjust the gas pressure if necessary.
12. With the valve position at 100%, insert the combustion analyzer probe into the flue probe
opening and allow enough time for the combustion analyzer reading to stabilize.