Site Preparation
AXP 1410 Installation and Use (6806800H70L)
64
3. Check the rails for proper alignment.
4. Check that the air filter is properly installed.
5. Check that the cable connections are secure and properly fitted.
6. Check the EMI gaskets for damage.
7. Check the items listed above for damage and report any damage or differences to
the customer service at
www.artesyn.com/computing/
.
8. Tighten loose screws before proceeding.
9. Remove the desiccant bags delivered together with the system and dispose of
them according to your country’s legislation.
2.2.2
Site and Installation Planning
Planning basic site and installation requirements you have to consider the following issues:
1. Is adequate power for the AXP 1410 system available?
2. Can the system be positioned in a way that -48 to -60V DC power source is easy to reach?
3. Are racks with sufficient space to install the system available?
4. Is suitable equipment available to lift the system into the rack?
5. Is there enough space to run a system console terminal? Is the cable long enough to reach
the system?
6. Are the inlet and outlet of the fans and therefore the airflow not blocked?
The product is thoroughly inspected before shipment. If any damage occurred during
transportation or any items are missing, please contact our customer's service immediately.