Using the optional storage tank and pumpout system, Remove shipping packaging, Open oil circuit valves – Carrier 19XL User Manual

Page 126: Torque all gasketed joints

background image

absolute pressure manometer or wet-bulb vacuum indicator (

Figure 25

)

500 v insulation tester (megohmmeter) for compressor motors with nameplate volt-
age of 600 v or less, or a 5000-v insulation tester for compressor motor rated above
600 v

Using the Optional Storage Tank and Pumpout System

Refer to

Pumpout and Refrigerant Transfer Procedures

section for: pumpout system

preparation, refrigerant transfer, and machine evacuation.

Remove Shipping Packaging

Remove any packaging material from the control center, power panel, guide vane actuator,

motor cooling and oil reclaim solenoids, motor and bearing temperature sensor covers, and the

factory-mounted starter.

Open Oil Circuit Valves

Check that the oil filter isolation valves (

Figure 4

) are open by removing the valve cap and

checking the valve stem.

Torque All Gasketed Joints

Gaskets normally have relaxed by the time the machine arrives at the jobsite. Tighten all

gasketed joints to ensure a leak tight machine.

Click here for Figure 25 — Typical Wet-Bulb Type Vacuum Indicator