beautypg.com

Ice build initiation – Carrier 19XL User Manual

Page 106

background image

temperature being less than the ICE BUILD SETPOINT, opening of the REMOTE CONTACT

inputs from an ice level indicator, or reaching the end of the Ice Build Time Schedule.

Ice Build Initiation

The Ice Build Time Schedule provides the means for activating ice build. The ice build time

table is named OCCPC02S.

If the Ice Build Time Schedule is OCCUPIED and the ICE BUILD OPTION is ENABLED, then

ice build is active and the following events automatically take place (unless overridden by a

higher authority CCN device):

1. Force CHILLER START/STOP to START.

2. Force WATER/BRINE CONTROL POINT to the ICE BUILD SETPOINT.

3. Remove any force (Auto) on the ACTIVE DEMAND LIMIT.

Note: Items 1-3 (shown above) shall not occur if the chiller is configured and operating as a lag

or standby chiller for lead/lag and is actively controlled by a lead chiller. The lead chiller

communicates the ICE BUILD SETPOINT, desired CHILLER START/STOP state, and

ACTIVE DEMAND LIMIT to the lag or standby chiller as required for ice build, if config-

ured to do so.